<cite id="9hzdh"></cite>
<var id="9hzdh"><video id="9hzdh"><thead id="9hzdh"></thead></video></var>
<cite id="9hzdh"></cite>
<var id="9hzdh"></var> <var id="9hzdh"><video id="9hzdh"></video></var>
<var id="9hzdh"><video id="9hzdh"></video></var>

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun announced today that underground development at the Kakula Copper Mine totalled 1,842 metres in August, bringing the cumulative total underground development completed to date to more than 20.6 kilometres – approximately 6.0 kilometres ahead of schedule.

The majority of the underground development headings at the Kakula Mine currently are traversing medium-grade sections of the orebody, with average grades ranging between 3% and 5% copper. A concentrated effort was made in August to complete the ledging development in the room-and-pillar section of the mine to accommodate critical infrastructure, such as piping and electrical cabling, for the mine’s permanent water-handling system.

The ledging development work will be completed early this month and will allow the mining teams to begin highly-productive stoping operations; however, the development work was in lower-grade ore and resulted in a temporary, modest decrease in overall stockpile grade in August and early September.

The stockpile grade is expected to improve, as planned, beginning this month as the majority of the working areas will transition to the higher-grade ore zones near the centre of the deposit that have copper grades approximately +5% to +8%.

The beneficial handover of the high-capacity ore conveyor system at the Kakula North declines was achieved at the end of July. All of the ore being mined in the northern portion of the Kakula Mine now is transported to surface via the conveyor system and placed on a blended, run-of-mine surface stockpile. The blended stockpile contains 483,000 tonnes grading an estimated 3.76% copper; comprised of 116,000 tonnes of high-grade ore grading 6.08% copper and 367,000 tonnes of medium-grade ore grading 3.02% copper.

Two additional, pre-production ore stockpiles are located at the Kakula South decline (approximately 121,000 tonnes grading 2.36% copper) and the Kansoko decline (approximately 68,000 tonnes grading 2.21% copper). More than 109,000 tonnes of ore was added to the project’s pre-production stockpiles in August.

Surface conveyor systems to transport the ore from the Kakula North stockpile to the processing plant are under construction.

First copper production expected in less than a year

Initial production at the Kakula Mine is scheduled for Q3 2021. Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 million tonnes per annum (Mtpa) at an estimated average feed grade well in excess of 6% copper over the first five years of operation.

The Kakula Mine will have one of the most favourable environmental footprints of any tier-one copper mine anywhere in the world. The mine will be powered by clean, renewable hydroelectricity and be among the world's lowest greenhouse gas emitters per unit of copper produced. Kakula also will have a relatively small surface footprint as approximately 55% of the mine’s tailings will be pumped back into underground workings.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the DRC government (20%).

“Together with our joint-venture partners, we look forward to sharing the independently verified engineering and economic studies on September 8th that will showcase why Kamoa-Kakula is, without question, the world’s best new copper project,” said Mr. Friedland. “Kamoa-Kakula is unique as it combines ultra-high-copper grades with thick, shallow, flat-lying ore zones, providing the economies of scale and low mining costs of large, open-pit mining operations, but without the visual environmental impact associated with open-pit mining.”

“We also plan to soon announce the appointment of a leading environmental consulting firm to audit Kamoa-Kakula’s greenhouse gas intensity metrics, providing Environmental, Social and Governance investors with independent and transparent verification of the project’s achievements towards our goal of producing the world’s greenest copper,” Mr. Friedland added.

Aerial view of the Kakula Mine showing the tonnes and grade of the main pre-production stockpiles at the northern declines. The stockpile currently contains approximately 483,000 tonnes grading 3.76% copper; comprised of approximately 116,000 tonnes at 6.08% copper and 367,000 at 3.02% copper.

Kakula southern decline medium-grade ore stockpile currently containing approximately 121,000 tonnes grading 2.36% copper.

Kansoko decline medium-grade ore stockpile currently containing approximately 68,000 tonnes grading 2.21% copper.

Kakula Mine development progressing towards zone of +8% copper in centre of deposit

Underground development of the Kakula Mine – the first of multiple, near-surface copper deposits that are planned to be put into production on the 400-square-kilometre Kamoa-Kakula mining licence – is now significantly ahead of schedule. Mine access drives 1 and 2 (interconnected, parallel tunnels that will provide access to ore zones) being driven from the Kakula northern declines continue to advance towards the southern portion of the orebody.

Development of the eastern perimeter drives also is well advanced as are the access drives to the room-and-pillar mining area. Development of twin access drives being driven from Kakula’s southern portal has reached the +5% copper mining zone, with mining crews working to establish the connection of these drives with mine access drives 1 and 2 from the northern side of the orebody. The northern and southern access drives are expected to join in November 2020, which will be a major milestone in the development of the Kakula orebody.

Once the northern and southern access drives are connected, the majority of mining activities will focus on the initial drift-and-fill mining blocks in the centre of the Kakula deposit, where the average grade is higher than 8% copper. Drift-and-fill stoping is a highly-efficient form of underground mechanized mining and will allow the operation to efficiently recover significantly more tonnes from the orebody.

Underground mining with two mining crews also is taking place at the Kansoko Mine, located at the Kamoa deposit, approximately 10 kilometres north of the Kakula Mine.

The construction of Kakula’s second permanent underground water-handling system is nearing completion with the first of four pump trains commissioned in early August; the second pump train was commissioned in the last week of August. The new system adds 800 litres per second of underground pumping capacity, bringing the total installed capacity to 1,400 litres per second. Two additional underground water dams are under construction; one at bottom of the southern declines, and one along the north eastern perimeter drifts.

Ivanhoe plans to issue the independent definitive feasibility study for the development of the 6 Mtpa Kakula Mine on September 8, 2020. The company also will issue a pre-feasibility study, including mining 1.6 Mtpa from the Kansoko Mine, to take full advantage of an expanded plant capacity of 7.6 Mtpa at Kakula. In addition, the company will issue an updated, expanded preliminary economic assessment for the overall development plan of up to 19 Mtpa for all of the copper discoveries made to date at the Kamoa-Kakula Project.

Martin Nkulu, conveyor belt attendant, monitoring high-grade copper ore being delivered to surface via the Kakula North decline conveyor, which has the capacity to transport 2,000 tonnes of ore an hour.

A load of copper ore being transported up the Kakula South decline. One of the two southern access drives has entered the +5%-copper mining zone, while the other will enter it shortly. The southern access drives are expected to join the northern access drives in November.

Kasongo Mahji at a surface settling pond for Kakula’s second permanent underground dewatering pipe system that was commissioned in early August.

Figure 1: The eastern portion of Kakula Mine ─ representing less than half of the overall 13.3-kilometre-long Kakula Deposit ─ overlain on southern Manhattan Island to give a sense of the scale of the underground operations.

Figure 2: Underground development completed to the end of July (in black) and scheduled development (green, brown, blue & black) until September 30, 2020. Shown are the 3%, 5% and 8% copper contours and the location where the northern and southern access drives are scheduled to join in November 2020 (red circle).

Figure 3: Underground development completed to the end of July (in black) and scheduled mine development over the three months ending December 31, 2020. Majority of the development during this period will be in the initial drift-and-fill mining area within Kakula’s high-grade zone (+8% copper).

Construction on the processing plant and other surface infrastructure rapidly progressing

Construction of Kakula’s initial, 3.8-Mtpa concentrator plant is progressing well, with approximately 20,000 cubic metres of concrete being poured to date. Concrete bases for the ball mills, flotation plant and the concentrate thickener have been partially handed over to the mechanical contractor to commence installation work, and mechanical erection and installation is underway in most of the plant areas. Structural steel fabrication is complete with more than half of the approximately 6,000 tonnes of structural steel already delivered to site. Fabrication of platework and piping is progressing according to schedule with the first deliveries already on site; platework installation has started.

Total steel prefabricated or installed is approximately 2,000 tonnes. All floor and sidewall plates for the concentrate thickener now are in position, and welding is 40% complete.

Installation of the tailings thickener has commenced, with the centre column being placed in position and welding of the floor plates underway. Pre-assembly of the high-pressure grinding rolls feed bin #1 conveyor has started. Both secondary crushers have been assembled and placed in position. Installation of the first ball mill shell has been completed.

All 21 oversized truck loads of equipment for the processing plant’s primary ball mill ? measuring 9.75 metres (32 feet) long and 6.1 metres (20 feet) in diameter – have arrived on site. The final shipments of the ball mill components are scheduled to arrive at site this month, which will be the final deliveries of long-lead plant equipment.

Beijing-based CITIC Construction is building Kakula’s first-phase, backfill paste plant. The backfill plant will be used to blend tailings from the processing plant with cement to produce paste backfill. The backfill will be pumped back into the mine and used to help support mined-out areas. Approximately 55% of the mine’s tailings will be sent back underground, significantly reducing the surface tailings storage.

Construction of the tailings dam has commenced and is progressing well; with the aim to complete most of the earthworks before the rainy season starts in November.

Led by the 400-tonne crane, a convoy of trucks carrying steel and equipment en route to the Kamoa-Kakula Project. The last truckloads of long-lead items for the processing plant are expected to arrive at site before the end of September.

Ongoing construction of Kakula’s 3.8-Mtpa processing plant. Members of Kamoa-Kakula’s construction team in front of one of the ball mill shells prior to it being lifted into place by a 400-tonne crane (second picture below).

To view a short, time-lapse video of the installation of the first of three ball mill shells, click here: https://vimeo.com/451270670

The 400-tonne crane lifts a platform section for the flotation cells into positon.

Installation of the discharge end and trunnion for the primary ball mill.

Installation of the secondary crushers at the processing plant.

Contract employees assembling the processing plant’s concentrate thickener.

Discussions underway for the marketing of Kakula’s copper concentrates

Kamoa-Kakula is in detailed discussions with a number of parties with respect to the marketing and smelting of its copper concentrates. Kakula is expected to produce an extremely high-grade and clean copper concentrate that will be highly coveted by copper smelters around the world. Metallurgical test work indicates that the Kakula concentrates contain extremely low arsenic levels by world standards – approximately 0.01%.

Clean, sustainable hydro-electric power for Kamoa-Kakula

Construction activities at the Mwadingusha hydro-electric power plant, where all six turbines are being replaced, is progressing well; as is the associated 220-kilovolt (kV) infrastructure to supply Kamoa-Kakula with clean hydro-power. The mine is scheduled to be energized with permanent 220kV hydro-generated power in early 2021, well in time for first copper production.

The temporary construction power supply for the Kakula Mine was recently upgraded, including the commissioning of six 2-megawatt (MW) generators to provide back-up power, and the installation of an 18 MW/120-kilovolt (kV) mobile substation to increase the capacity of grid power available at the mine. This will provide sufficient power until the main 220kV power supply is energized. An additional six new 2MW generators have arrived at the port of Durban from China, and are en route to site. The twelve generators will supply the full back-up power requirements for the mine.

Construction of the 220kV supply infrastructure is in progress, including a new 220kV distribution sub-station for the power utility (SNEL); a new 35-kilometre, 220kV power line; and a consumer substation at Kakula with two 80 MW/220kV transformers.

Installing a new alternator in the Mwadingusha hydro-electric power plant. Mwadingusha will soon be delivering 72 MW of clean, sustainable hydroelectricity to the national grid.

Kamoa-Kakula’s COVID-19 readiness initiatives focused on risk mitigation

In accordance with new health guidelines from the DRC government, and in line with the country’s lifting of restrictions, Kamoa-Kakula lowered its quarantine and lockdown measures from level 3 to level 2 on July 27th. The mine’s Congolese workforce have gone back to normal rotation. Rigorous testing, physical distancing, wearing face masks, frequent hand washing and contact tracing measures are still in place to protect the safety and health of the workforce and community members. All expatriate employees are still required to quarantine for two weeks upon arrival at Kamoa-Kakula.

The project has established a COVID-19 isolation facility at the Kamoa camp. Any potential symptomatic patients are moved to this facility, where they will be isolated, tested and treated. Once the patient has recovered and is deemed no longer infectious, they can return to work only after an additional quarantine period determined by the project’s medical staff in dedicated quarantine.

As the pandemic evolves, the medical team at Kamoa-Kakula is purposefully reviewing and updating its risk mitigation protocols. The project’s preventative measures are at the highest international standards and, if there was a case internally, the risk of spreading or cross-contamination is very low.

Members of a community women's group that owns and operates a banana plantation near the Kamoa-Kakula Project. The plantation is one of Kamoa-Kakula’s initiatives to enhance food security in nearby communities.

Qualified Persons

Disclosures of a scientific or technical nature regarding development scenarios at the Kamoa-Kakula Project in this news release have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is the Head of the Kamoa Project. Mr. Amos has verified the technical data disclosed in this news release.

Other disclosures of a scientific or technical nature in this news release have been reviewed and approved by Stephen Torr, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not considered independent under NI 43-101 as he is the Vice President, Project Geology and Evaluation. Mr. Torr has verified the other technical data disclosed in this news release.

The stockpile grade estimates contained in this release are based upon bulk ore sampling from underground headings. Sampling is done on each heading every second blast and three 5-kilogram samples are taken. The samples are pulverized at the project’s onsite laboratory and analyzed used using a portable XRF (pXRF) instrument. Kamoa Copper has routinely analyzed its exploration drill core for copper using pXRF, in addition to analysis at a commercial laboratory using four acid digest and ICP-OES. This data has demonstrated that pXRF results can be relied upon for grade control and run-of-mine sampling.

Ivanhoe has prepared a current, independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, which is available on the company’s website and under the company’s SEDAR profile at www.sedar.com:

  • The Kamoa-Kakula 2020 Resource Update dated March 25, 2020, prepared by OreWin Pty Ltd., Wood plc, DRA Global, SRK Consulting (South Africa) (Pty) Ltd and Stantec Consulting International LLC.

The technical report includes relevant information regarding the assumptions, parameters and methods of the mineral resource estimates on the Kamoa-Kakula Project cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release.

Information contacts

Investors: Bill Trenaman +1.604.331.9834 / Media: Matthew Keevil +1.604. 558.1034

Forward-looking statements

Certain statements in this release constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. These statements reflect the company’s current expectations regarding future events, performance and results and speak only as of the date of this release.

Such statements include without limitation, the timing and results of: (i) statements regarding the Definitive Feasibility Study for the Kakula Mine, and an updated Integrated Development Plan for multiple expansions of the entire Kamoa-Kakula mining licence, planned to be issued on September 8, 2020; (ii) statements regarding as Kakula’s underground development progresses over the next few months, the majority of the working areas are expected to transition into the higher-grade ore zones near the centre of the deposit that have copper grades approximately 5% to 8%; (iii) statements regarding initial production at the Kakula Mine is scheduled for Q3 2021; (iv) statements regarding Kakula is projected to be the world’s highest-grade major copper mine with an initial mining rate of 3.8 million tonnes per annum (Mtpa) at an estimated average feed grade in excess of 6% copper over the first five years of operation; (v) statements regarding the Kakula Mine will have one of the most favourable environmental footprints of any tier-one copper mine; (vi) statements regarding the Kakula Mine will be powered by clean, renewable hydroelectricity and be among the world's lowest greenhouse gas emitters per unit of copper produced; (vii) statements regarding Kakula will have a relatively tiny surface footprint as approximately 55% of the mine’s tailings will be pumped back into underground workings; (viii) statements regarding the last truckloads of long-lead items for the processing plant are expected to arrive at site before the end of September; (ix) statements regarding as underground development progresses at the Kakula and Kansoko mines over the next few months, the grade of the project’s three medium-grade stockpiles is forecast to increase to between 3% - 5% copper; (x) statements regarding the northern and southern access drives at Kakula are expected to be joined in November 2020; (xi) statements regarding in roughly one year, the Kakula Mine will be producing extremely high-grade concentrate containing over 55% copper with essentially zero arsenic; (xii) statements regarding Kamoa-Kakula is unique as it combines ultra-high-copper grades with thick, shallow, flat-lying ore zones, providing the economies of scale and low mining costs of large, open-pit mining operations, but without the environmental scarring often associated with open-pit mining; and (xiii) statements regarding the Kakula mine is scheduled to be energized with permanent 220kV hydro-generated power in early 2021.

As well, all of the results of the pre-feasibility study for the Kakula copper mine and the updated and expanded Kamoa-Kakula Project preliminary economic assessment constitute forward-looking statements or information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xiv) changes in project scope or design, and (xv) political factors.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and under “Risk Factors”, and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

Although the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.

The company’s actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth below in the “Risk Factors” section in the company’s Q1 2020 MD&A and its current annual information form.

剛果民主共和國科盧韋齊 — 艾芬豪礦業 (TSX: IVN; OTCQX:IVPAF) 聯席董事長羅伯特·弗里蘭德 (Robert Friedland) 與孫玉峰 (Miles Sun) 今天宣布,卡庫拉銅礦的地下開發持續快速推進,于8月份共掘進1,842米,迄今為止已經完成了20.6公里以上的地下開拓工程,超過既定目標約6.0公里。

目前,卡庫拉礦山的大多數開拓巷道橫貫中品位的礦段,其平均銅品位在3%5%之間。項目于8月份著重在礦山房柱式采礦區建設壁架,以容納礦山永久水處理系統的管道和電纜等重要基礎設施。

壁架工程將于本月初完成,使采掘班組可以盡快展開高效的采礦作業。然而,工程位置的礦石品位較低,因此8月份至9月初的礦堆品位將會暫時稍為下跌。

大多數工作區將于本月過渡到礦床中心附近的高品位礦區,銅品位約為+5%至+8%。因此,礦堆的品位將按計劃進度而有所提升。

卡庫拉北部斜坡道的高負載礦石輸送系統,已于7月底正式運行。目前,所有在卡庫拉礦山北部開采的礦石將經由輸送系統運送到地表的混合礦堆?;旌隙褕瞿壳耙褍涞V石量約483,000噸,銅品位約3.76%,其中包括116,000噸的高品位礦石 (銅品位6.08%) 以及367,000噸的中品位礦石 (銅品位3.02%)。

此外,項目還有兩個額外的投產前礦堆位于卡庫拉南部斜坡道 (121,000噸礦石,銅品位2.36%) Kansoko斜坡道 (68,000噸礦石,銅品位2.21%)。于8月份,項目的投產前礦堆已增加超過109,000噸礦石。

地表輸送系統的施工正在進行中,將從卡庫拉北部的礦堆的礦石運送到選礦廠。

首批銅精礦生產將于一年內實現

卡庫拉礦山計劃于2021年第三季度實現首批精礦生產,預期將會成為全球品位最高的大型銅礦,初始年處理礦量為380萬噸,估計投產后頭5年的平均給礦銅品位達6%以上。

相比任何頂級銅礦,卡庫拉將會是具有最佳環境足跡的礦山之一。它將使用清潔、可再生的水電,并將成為全球每單位銅的溫室氣體排放量最低的礦山之一。礦山約55%的尾礦將被泵送回地下,卡庫拉的地表足跡因此相對較小。

卡莫阿-卡庫拉銅礦項目是艾芬豪礦業(占股39.6%)、紫金礦業集團(占股39.6%)、晶河全球(占股0.8%) 及剛果政府(占股20%) 的合資項目。

弗里蘭德先生說﹕我們期待于98日與我們的合資伙伴一起向外界公布卡莫阿-卡庫拉項目的獨立核實的工程和經濟研究報告,幫助大家了解卡莫阿-卡庫拉為何會是全球最為優秀的新建銅礦項目???/strong>-卡庫拉是獨一無二的,擁有厚大、接近地表和平伏的礦體和超高的銅品位,適合進行大型的露天采礦作業,易于實現規模效益和低采礦成本,且不會造成像露天采礦一樣的、可見的環境影響。

弗里蘭德先生補充說﹕我們還計劃馬上宣布聘請一家領先環保顧問公司的消息,該公司將負責審查卡莫阿-卡庫拉將會產生的溫室氣體強度指標,向關切環境、社會責任和企業治理的投資者提供獨立和透明的調研結論,以證明我們為達到生產世界上最環保銅金屬之一目標所做出的成績。

卡庫拉礦山的鳥瞰圖,顯示北面斜坡道的主要投產前堆礦。目前,該礦堆儲備礦石量約483,000 噸,銅品位3.76%,其中包括116,000噸,銅品位6.08%的礦石和367,000噸,銅品位3.02%的礦石。

卡庫拉南面斜坡道的中品位堆礦,目前儲備礦石量約121,000噸,銅品位2.36%。

Kansoko斜坡道的中品位堆礦,目前儲備礦石量約68,000噸,銅品位2.21%。

卡庫拉礦山持續推進開發,將到達礦床中心銅品位8%以上的礦段

卡庫拉礦山是卡莫阿-卡庫拉項目涵蓋的400平方公里開采許可范圍內多個近地表銅礦的首產礦山,地下開采工程持續超計劃高效推進。礦山的1號和2號運輸通道正從卡庫拉北面斜坡道朝著礦體的南部掘進,施工進展順利。兩條運輸通道是相互連接的平行通道,將連通至開采礦段。

同時,東部外圍通道和房柱式采礦區的工程的進展也十分理想。兩條運輸通道已從卡庫拉南部礦坑口到達銅品位高于5%的開采礦段,采掘班組正在將這兩條通道與礦體北部的1號和2號運輸通道連接。南北運輸通道預計于202011月連接完成,將會是卡庫拉礦體開拓工程的重要里程碑。

南北運輸通道連接后,大多數的采礦活動將會集中在卡庫拉礦床中心的首個分層充填采礦區,該礦區的平均銅品位達8%以上。分層充填采礦是一種高效的機械式地下采礦法,可有效地大大提升從礦體采掘的礦石量。

位于卡庫拉礦山以北約10公里,卡莫阿礦區范圍內的Kansoko礦山,目前正有兩隊采掘班組在進行地下采礦工程。

卡庫拉第二永久地下水處理系統的施工將近完成。系統設有4個泵組,第1個泵組已于8月初運行,而第2個泵組也于8月最后一個星期開始運行。新系統將地下泵流量提升每秒800公升,使總裝置容量達到每秒1,400公升。目前正在加建兩個地下水壩,一個位于南面斜坡道的底部,另一個則沿著東北面的周邊平巷建造。

艾芬豪計劃于202098日發布卡庫拉礦山年處理礦量600萬噸開發工程的獨立最終可行性研究報告。同時,公司將會發布包含Kansoko礦山 (年開采礦量160萬噸) 的預可行性研究報告,以充分利用卡庫拉礦區將擴建至年處理礦量760萬噸的選廠產能。此外,公司還將發布卡莫阿-卡庫拉項目至今所有銅礦資源的整體開發計劃(年處理礦量可達1,900萬噸) 的更新和擴充的初步經濟評估報告。

輸送帶工Martin Nkulu正在監控高品位銅礦石經卡庫拉北面斜坡道的輸送系統運送到地表,該輸送系統每小時可輸送2,000噸礦石。

一臺裝載著銅礦石的卡車駛向卡庫拉南面的斜坡道。其中一條南部運輸通道已進入銅品位高于5%的開采礦段,另一條也快將到達。南北運輸通道預計于11月連接完成。

Kasongo Mahji在卡庫拉第二永久地下排水管道系統的地表沉淀池,該系統已于8月初開始運行。

1:卡庫拉礦山東部地區的礦體走向長度占卡庫拉礦床總長度13.3公里的將近一半,其地下作業的規模之大,相當于可以覆蓋曼哈頓島南部區域。

2:截至7月底已完成的地下開拓工程 (黑色),以及計劃在2020930日前完成的開拓工程 (綠色、棕色、藍色和黑色)。圖中顯示銅品位3%、5%8%的等值線,以及計劃于202011月完成連接的南北運輸通道位置 (紅圈)。

3:截至7月底已完成的地下開拓工程 (黑色),以及計劃在截至20201231日止三個月內進行的礦山開拓工程。這段期間,大部分開拓工程將在卡庫拉高品位礦區 (銅品位8%以上) 的首個分層充填采礦區進行。

選礦廠和其他地表基礎設施的施工快速推進

卡庫拉年處理礦量 380 萬噸選礦廠的施工進展順利,至今已灌入20,000立方米以上的混凝土。球磨機、浮選廠和精礦濃密機的混凝土底座部分已交給機械承包商開始進行安裝,且大部分廠房區域正在搭建鋼架。約有6,000噸的鋼結構已制造完成,其中一半以上的鋼結構已運抵礦場。板金和管道的制造正按計劃進行中,首批貨運已抵達礦場,并已開始安裝板金。

預制和已安裝的鋼材合共約有2,000噸。目前,精礦濃密機的所有底板和側墻板已確定位置,且已完成40%的焊接工作。

尾礦濃密機已開始進行安裝,中柱已放到指定位置,并正進行底板的焊接。高壓輥磨機礦倉的1號輸送系統已開始預先組裝。兩臺二段破碎機都已組裝并放到指定位置。第一臺球磨機的外殼已完成安裝。

裝載著選礦廠主要球磨機(9.75/32英尺、直徑6.1/20英尺) 設備的21輛大型卡車已運抵礦場。最后一批的球磨機組件計劃于本月運抵礦場,這將會是最后一批需要運輸的長周期設備。

北京的中信建設正在興建卡庫拉第一期的回填廠?;靥顝S將選礦廠的尾礦與水泥混合制造回填漿?;靥顫{將會泵回礦山用作填充采空區。礦山約55%的尾礦將被泵送回地下,大大減少地表的尾礦量。

尾礦壩已開始施工且進展順利,目標是要在11月雨季開始前完成大部分的土方工程。

卡車車隊在一臺載重400噸的起重機帶領下,正裝載著鋼材和設備駛向卡莫阿-卡庫拉項目。最后一批選礦廠的長周期設備預計將于9月底之前運抵礦場。

正在施工的卡庫拉380萬噸/年產能選礦廠???/strong>-卡庫拉施工團隊成員在其中一臺球磨機的外殼前方。下方第二張圖片顯示一臺載重400噸的起重機將球磨機外殼安放到指定位置。

關于安裝第一臺球磨機外殼 (共三臺) 的簡短快放視頻可在此處觀看:https://vimeo.com/451270670

一臺載重400噸的起重機將浮選廠的工作臺放到指定位置。

工作人員正在安裝主要球磨機的出料裝置和耳軸。

工作人員在選礦廠安裝兩段破碎機。

承包商的員工在選礦廠組裝精礦濃密機。

關于卡庫拉銅精礦銷售方案的討論正在進行中

目前,卡莫阿-卡庫拉正與多方就銅精礦的銷售和冶煉方案進行詳細討論??◣炖瓕a極高品位的清潔銅精礦,將會是世界各地銅冶煉廠渴求的高質量產品。冶金測試結果顯示,按全球標準,卡庫拉精礦的含砷量極低,約為0.01%。

卡莫阿-卡庫拉項目的清潔、可再生水電

Mwadingusha 水電廠的施工進度可觀,當前正在進行全部6臺渦輪機的更換。同時,220千伏的相關基礎設施工程進展順利,將為卡莫阿-卡庫拉礦山提供清潔的水電能源供給。計劃于2021年初達到220千伏永久性水力發電能力,其時間表預計將與礦山的首批銅精礦生產進度完美匹配。

卡庫拉礦山的臨時建設電源最近已進行升級,包括已調試62兆瓦發電機用作后備電源,并已安裝18兆瓦/ 120千伏的移動變電站,以增加礦山可用的電網容量。這將在220千伏主要電力投入使用前提供足夠的電力。另外6臺新的2兆瓦發電機已從中國抵達南非德班港口,目前正在運送途中。這12臺發電機將為礦山提供足夠的后備電源供給。

220千伏供電基礎設施的建設正在進行中,包括﹕用于剛果國家電力公司(SNEL) 220千伏新配電變電站、一條35公里長的220千伏新輸電線,以及一座位于卡庫拉的用戶變電站 (設有兩個80兆瓦 / 220千伏的變壓器)。

工作人員正在Mwadingusha水電廠安裝一臺新的交流發電機。 Mwadingusha不久將會向國家電網提供 72兆瓦的清潔、可再生水電。

卡莫阿-卡庫拉項目的COVID-19應對舉措以減低風險為重點

根據剛果政府的新衛生指引,并配合該國解除的部分限制,卡莫阿-卡庫拉于727日將其檢疫和封鎖隔離措施從第3級降低到第2級。礦山的剛果員工已經恢復正常的換班安排。礦山繼續實施防疫措施如嚴格測試、保持距離、配戴口罩、經常洗手和接觸者追蹤調查等,以保護員工和社區成員的安全和健康。所有外籍員工抵達卡莫阿-卡庫拉后仍需進行兩個星期的檢疫隔離。

項目已在卡莫阿營地設有COVID-19隔離設施。任何疑似或出現病癥的人員都將會安排到該設施,進行隔離、檢測和治療?;颊呖祻颓也辉倬邆魅拘院?,只能在項目醫務人員訂立的額外隔離觀察期結束后才可返回工作崗位。

隨著疫情的變化,卡莫阿-卡庫拉的醫療隊伍正積極審閱和更新其疫情防控方案。項目的防疫措施符合最高國際標準,即使內部出現感染病例,傳播或交叉感染的風險也非常低。

卡莫阿-卡庫拉項目附近社區的女性組織成員持有和運營的香蕉種植園,作為卡莫阿-卡庫拉致力于提升附近社區食品安全的舉措之一。

合資格人士

本新聞稿中關于卡莫阿-卡庫拉項目開發方案的科學或技術性披露已經由Steve Amos 審查和批準,他憑借其教育、經驗和專業協會會籍被認為是NI 43-101 標準下的合資格人士。由于Amos先生是卡莫阿項目的負責人,因此他并不符合NI 43-101 對獨立人士的界定。Amos 先生已核實本新聞稿所披露的技術數據。

本新聞稿中的其它科學或技術性披露已經由 Stephen Torr 審查和批準,他憑借其教育、經驗和專業協會會籍被認為是 NI 43-101 條款下的合資格人士。由于 Torr 先生是項目地質和評估副總裁,因此他并不符合NI 43-101 對獨立人士的界定。Torr 先生已核實本新聞稿所披露的其它技術數據。

本報告所載的礦堆品位估算值是基于從地下巷道的大塊礦石取樣。每個巷道進行第二次爆破時取樣,并收集3個5公斤重的樣品。樣品在項目現場實驗室粉碎后,使用便攜式XRF (pXRF) 儀器進行分析。除了在商業實驗室利用4種酸分解液和ICP-OES進行分析之外,卡莫阿銅業也經常使用pXRF分析其鉆孔巖芯中的銅含量。該數據表明,pXRF結果可用于品位控制和采礦井取樣。

艾芬豪已經為卡莫阿-卡庫拉項目編制了一份符合NI 43-101 標準的最新獨立技術報告,該報告可在SEDAR 網站上的艾芬豪頁面獲得,網址為www.sedar.com

  • 2020年3月25日發布的2020年卡莫阿-卡庫拉資源更新,由OreWin Pty Ltd.、Wood plc、DRA Global、SRK Consulting (South Africa) (Pty) Ltd 和Stantec Consulting International LLC編制。

技術報告包括本新聞稿中引用的卡莫阿-卡庫拉項目的礦產資源估算的假設、參數和方法等信息,以及本新聞稿中關于科學和技術性披露的數據驗證、勘探程序和其他事項的信息。

聯系方式

投資者﹕Bill Trenaman +1.604.331.9834 / 媒體﹕Matthew Keevil +1.604. 558.1034

前瞻性陳述

本新聞稿載有的某些陳述可能構成適用于證券法所定義的“前瞻性陳述”或“前瞻性信息”。該等陳述及信息涉及已知和未知的風險、不明朗因素和其他因素,可能導致本公司的實際業績、表現或成就、其項目或行業的業績,與前瞻性陳述或信息所表達或暗示的任何未來業績、表現或成就產生重大差異。該等陳述可通過文中使用“可能”、“將會”、“會”、“將要”、“打算”、“預期”、“相信”、“計劃”、“預計”、“估計”、 “安排”、“預測”、“預言”及其他類似用語,或者聲明“可能”、“會”、“將會”、“可能會”或“將要”采取、發生或實現某些行動、事件或結果進行識別。這些陳述僅反映本公司于本新聞稿發布當日對于未來事件、表現和業績的當前預期。

該等陳述包括但不限于下列事項的時間點和結果﹕(i) 關于計劃于2020年9月8日公布卡庫拉礦山的最終可行性研究以及卡莫阿-卡庫拉開采許可范圍后續擴產的綜合開發計劃更新版的陳述;(ii) 關于在接下來幾個月,卡庫拉將繼續推進地下開發,預計大多數巷道將會到達礦床中心附近的較高品位礦段,銅品位約在5%與8%之間的陳述;(iii) 關于卡庫拉礦山計劃于2021年第三季度實現首產的陳述;(iv) 關于卡庫拉將會成為全球品位最高的主要銅礦,其初始年處理礦量為380萬噸,估計于首5年運營期間平均給礦銅品位達6%以上的陳述;(v) 關于卡庫拉相比任何頂級銅礦,將會是最有利于環境足跡的礦山之一的陳述;(vi) 關于卡庫拉礦山將會使用清潔、可再生的水電,并將成為全球每單位銅溫室氣體排放量最低的礦山之一的陳述;(vii) 關于卡庫拉礦山約55%的尾礦將被泵送回地下,地表足跡因此相對較小的陳述;(viii) 關于最后一批選礦廠的長周期設備預計于9月底之前運抵礦場的陳述;(ix) 關于在接下來的幾個月,卡庫拉和Kansoko礦山將繼續推進地下開發,預計項目的三個中品位礦堆將會提升銅品位至3%與5%之間的陳述; (x) 關于卡庫拉的南北運輸通道預計于2020年11月連接完成的陳述;(xi) 關于大約一年后,卡庫拉礦山將會生產出極高品位的精礦,銅品位達55 %以上且砷含量接近零的陳述;(xii) 關于卡莫阿-卡庫拉是獨一無二的,擁有礦體厚大、接近地表和平伏的礦體和超高的銅品位,適合進行大型的露天采礦作業,易于實現規模效益和低采礦成本,且不會造成像露天采礦一樣的可見環境影響的陳述;以及(xiii) 關于卡庫拉礦山計劃于2021年初達到220千伏永久性水力發電能力的陳述。

此外,卡庫拉銅礦預可行性研究的所有結果以及更新和擴展的卡莫阿-卡庫拉項目初步經濟評估,構成了前瞻性陳述或信息,并包括內部收益率的未來估算、凈現值,未來產量、現金成本估算、建議采礦計劃和方法、礦山壽命估計、現金流預測、金屬回收率、資本和運營成本估算,以及項目分期開發的規模和時間點。另外,對于與卡莫阿-卡庫拉項目開發有關的特定前瞻性信息,公司是基于某些不確定因素而作出假設和分析。不確定因素包括:(i) 基礎設施的充足性;(ii) 地質特征;(iii) 礦化的冶金特征;(iv) 發展充足選礦產能的能力;(v) 銅價格;(vi) 完成開發所需的設備和設施的可用性;(vii) 消耗品和采礦及選礦設備的費用;(viii) 不可預見的技術和工程問題;(ix) 事故或破壞或恐怖主義行為;(x) 貨幣波動; (xi) 法例修訂;(xii) 合資伙伴對協議條款的遵守情況;(xiii) 熟練勞工的人手和生產率;(xiv) 各政府機構對礦業的監管;(xv) 籌集足夠資金以發展該等項目的能力;(xiv) 項目范圍或設計更變;以及(xv) 政治因素。

前瞻性陳述及信息涉及重大風險和不確定性,故不應被視為對未來表現或業績的保證,并且不能準確地指示能否達到該等業績。許多因素可能導致實際業績與前瞻性陳述或信息所討論的業績有重大差異,包括但不限于“風險因素”以及本新聞稿其他部分所指的因素,以及有關部門實施的法律、法規或規章或其不可預見的變化;與本公司簽訂合約的各方沒有根據協議履行合約;社會或勞資糾紛;商品價格的變動;以及勘探計劃或研究未能達到預期結果或未能產生足以證明和支持繼續勘探、研究、開發或運營的結果。

雖然本新聞稿載有的前瞻性陳述是基于本公司管理層認為合理的假設而作出,但本公司不能向投資者保證實際業績會與前瞻性陳述的預期一致。這些前瞻性陳述僅是截至本新聞稿發布當日作出,而且受本警戒性聲明明確限制。根據相應的證券法,本公司并無義務更新或修改任何前瞻性陳述以反映本新聞稿發布當日后所發生的事件或情況。

基于本公司 2020年首季管理層討論與分析報告及其最新年度信息報告里的“風險因素”部分所指的因素,本公司的實際業績可能與這些前瞻性陳述所預計的業績產生重大差異。

Download in PDF Format

Subscribe to our Email List

女人与公牛做爰,nana高清在线观看,先锋影音亚洲中文字幕av,日本牲交大片免费观看
亚洲理论在线a中文字幕 s8视频 在线不卡日本v二区三区18 freshman中学 bt天堂www 夺冠在线观看免费观看完整版 神马电影院 麻豆传媒官网 天堂资源最新版在线 chinses中国女人china 妈妈的朋友7 小蝌蚪app下载大全小蝌蚪 欧美 av亚洲 av国产 制服 三级片在线 亚洲香蕉网久久综合影院 赠我予白 啵乐腐味满满 仙尊归来洛尘 哔咔漫画app下载 家庭教师动漫免费观看 国产在线视精品在亚洲 小蝌蚪视频 年轻母亲4 镇国战神叶君临免费阅读 xing8 噜噜射 free性欧美极度另类 欧美色色 快喵app下载官网 啵乐官网入口 秦始皇与阿房女高清版 第一次玩交换真实经历 我和黑大佬的365天高清中文翻译 向日葵视频app下载 国产肥熟女视频一区二区 娇艳都市未删减小说 叶不凡秦楚楚全文阅读免费阅读 顾轻舟司少帅免费阅读完整版百度小说 久久水蜜桃网国产免费网 人与性 67194成l人在线观看线路 gif动态图出处第900期 岳风柳萱更新最快 龚玥菲版新梅瓶在线观看 菠萝菠萝蜜手机网 丝瓜黄瓜视频在线观看视频 春光乍泄高清图 大胸年轻继坶在线播放 女人艾滋病的三大症状 将夜免费神马影院 趣播 秋霞电影网午夜鲁丝片无码 佛山市地图 欧美色在线精品视频 保险女王 十八以下岁女子毛片 好男人视频社区 age动漫官方网 汤姆叔叔的小屋 2012国语在线看免费观看 菠萝菠萝蜜免费影院 狠狠狠的在啪线香蕉亚洲 516事件是什么事件 爸爸的朋友 大香伊在人线免 附近的人妇女 成l人在线观看线路1 火车上爱爱好爽好刺激 age动漫 一胎双宝总裁大人夜夜欢全文免费阅读小说 青青河边草免费观看2019 噜噜射 小草免费观看在线 8个征兆说明你怀孕了 佛山房价 狠狠狠的在啪线香蕉亚洲 破外女出血在线视频高清在线 graphis图片 新翁熄粗大 微拍网 附近的妇女 磁力天堂 79电影网 菠萝菠萝蜜在线视频在线播放 三个未婚妈妈免费观看 禁止的爱善良的小在线观看 永恒国度 ttsp 西游记86版全集 第一次玩交换真实经历 国产香线蕉手机视频在线观看 妈妈的朋友2 中文字幕乱码免费 最强医圣林奇完整版 西瓜网 closeup毛茸茸pics大全 狠狠狠的在啪线香蕉亚洲 快猫短视频 草莓视频黄 性欧美欧洲老妇 六漫画 抖阴app 欧美 日韩 无码 有码 在线 prohub官网入口 黑白配视频在线观看 趣播 年轻护士2高清中文字幕 暖暖日本免费播放 新婚娇妻1一25李晶 美女被揉胸 男同性恋视频 67194成l人在线观看线路 艾草仙姑在线播放 夜猫视频 7752 小蝌蚪app下载大全小蝌蚪 17173 maomiav 皮肤黄适合穿这6个颜色 卡一卡二卡三免费视频 北地胭脂 蓝色导航 啵乐官方网站入口链接 hxc 365dni是真做吗 樱花视频 附近人妇女 国产香线蕉手机视频在线观看 一招判断艾滋病 蝶恋直播 姐姐的朋友3 汤姆叔叔的小屋 xiaav因你而精彩 骚虎影视 六漫画-好看的热门漫画 202z 叶不凡秦楚楚全文阅读免费阅读 日本道专区无码中文字幕 三个未婚妈妈免费观看 老八吃屎的视频 vultr美国与日本 chengren 2828 久久vs国产综合色 女朋友被窝里撒娇说要 黑白配视频在线观看 薰衣草视频高清在线观看 三级片在线观看 台湾自拍偷区亚洲综合 色妞基地 新婚娇妻宠上瘾 无尽长廊污的 影视大全免费观看全集 快猫下载 斗罗大陆免费观看 翁与小莹最新大结局 日本一区二区 bt磁力搜索天堂 97gan 磁力链bt磁力天堂 伊在香蕉国产在线视频 琉璃免费观看电视剧全集54 啵乐漫画app官网 graphis图片 99re8热视频这在线视频 偷偷藏不住 全文免费 色偷偷色偷偷色偷偷在线视频 欧美日韩无线码免费 樱桃小视频 元气骑士破解版下载2020最新版本 啵乐网页 年轻的小婊3中文字 18中国帅同志chinatv 色咯咯 杨贵妃秘史 农门长姐有空间 木瓜网 老子影院 sezhan 熟女少妇人妻中文字幕 日本不卡免费一区二区 拍摄指南 杂烩大乱炖目录 msn日本 可播放欧美同性freebest mm131 菠萝菠萝蜜视频在线观看 久久er热在这里只有精品66 uoco 菠萝视频香蕉视频 小鬼翔太 都市仙尊洛尘最新章节更新 汅动漫在线观看全集免费 佛山市公安局 十八以下岁女子毛片 足浴按摩的行话黑话 仙尊归来洛尘 蝴蝶论坛 无尽长廊污的 肉超级多的糙汉文 香蕉一本大道中文在线 慈禧的秘密生活 欧美 av亚洲 av国产 制服 japanesefree中国寡妇 洁癖的禁欲医生 玉米视频 艾草仙姑 凌依然易谨离小说全文阅读的小说 公憩28篇小说 月光影视 郑艳丽 哔咔漫画 北地胭脂 偷偷藏不住.txt百度云 原始的冲动 致命的你漫画在线观看全集免费 平民影院 甜美的咬痕被禁的一话 香蕉人人超人人超碰超国产 无尽长廊lol王者荣耀 影视大全最新免费版 天天爱去 在线录播 xiaosese 日本免费一区 饥渴的40岁熟妇完整版在线 色戒无删除158分钟完整版 中国黄页大全 菠萝视频香蕉视频 烈火动漫 一品道门在线播放 中国雅虎 附近人妇女 我的美女房东免费观看 寡妇和大狼交 抖阴下载 秋霞电影网鲁丝片无码2020 淘气天尊博客新浪 北娃大王 中国白胖肥熟妇bbw 玖玖热 漂亮女人在线全集免费 推荐50本熬夜看完的小说 2020年最新cl地址入口 噜噜射 67194成l人在线观看线路 莎翁情史 荡乱绝顶3p在线观看 中文字幕第一页 182tv免费播放线路一线路二 欧美色在线精品视频 laoyawo 肥肉 小说 看巴士西瓜钙片钙片 抖阴下载 足浴按摩的行话黑话 皮特影院 快猫短视频 身为人母电影在线观看 年轻母亲2 幸福花园 国产乡下三级全黄三级 六漫画 中文字幕 人妻熟女 叶凡秋沐橙 bbox撕裂bass 小玲和她的公全文阅读 365dni 超级全能学生 斗罗大陆免费看 都市仙尊免费阅读洛尘 顾轻舟司行霈完整版全文免费阅读 茄子视频app下载 青青河边草新视频免费观看 抖阴下载 天堂资源最新版 佛山交警信息服务网 亚洲中文字幕永久在线 大香伊在人线免 小泽玛丽亚 男同性恋视频 秋霜在线观看高清视频 父爱如山动漫 色豆网 欧美色视频日本片免费 人与性 高清视频录播服务器器 性欧美欧洲老妇 中文字幕 人妻熟女 妈妈的朋友7 三级片在线观看 绿色椅子 精品国产自在天天线2019 月光影视在线观看 战狼影院 日本无码一区 佛山 善良的小峓子完整视频 啵乐app 玖玖热 都市仙尊洛尘最新更新 中国白胖肥熟妇bbw wuwubox 一看就舒心的图片 日本不卡免费一区二区 超级陈扬最新章节更新 国产精品每日更新在线 国产毛片农村妇女系列bd版 freshman中学 天狼影院 三级网 17173 征兵网 xiaosese 67194线路1(点击进入) 秋霞电影网午夜免费鲁丝片 新翁熄粗大 q友乐园女生头像 淘气天尊新浪博客 好吊妞 汅动漫在线观看全集免费 向日葵视频下载 秋霞电影网午夜鲁丝片无码 顾轻舟 小草在线影院观看在线播放 北岛玲 幸福花园 秋霞影院 日本无码一区 欧美videosgratis杂交 年轻的母亲在线观看 国产香线蕉手机视频在线观看 斗罗大陆4终极斗罗求书阁 欧美观看免费全部完 日本樱花服务器 啵乐漫画app官网 亚洲 无码 在线 专区 小蝌蚪视频 琉璃免费观看电视剧全集 33eee 佛山交警信息服务网 欲望妹妹 四虎最新2019入口地址 艾草仙姑在线播放 草逼 飞极速在线 北地胭脂 啊 cao死你个浪货 美女性爱 情欲满载 天堂资源最新版 啦啦啦视频在线观看视频 另类专区av无码 202z 非会员试看120秒体验区 最大胆人体艺术图片 虫爱少女 欲望妹妹 yellow高清在线观看 年轻的小峓子4中字 书房宠婢 叶凡秋沐橙小说 国产野外无码理论片在线观看 姐姐的朋友3 陈说美食 年轻母亲4 都市修仙洛尘最新章节 被黑化的前任们抓住了 都市仙尊洛尘最新章节更新 365dni是真做吗 菠萝菠萝蜜手机网 17173dnf专区 日本樱花服务器 在线不卡日本v二区三区18 影视大全最新免费版 一本到高清在线视频观看 啵乐官方网站入口链接 男生最经不起女生哪种撩 折腰蓬莱客肉肉 亚洲色tu 菠萝菠萝蜜视频在线播放官网 chinses中国女人china 蓝色导航 年轻的女教师 新婚娇妻1一25李晶 榴莲视频下载 趣播 都是仙尊洛尘免费阅读 亚洲中文字幕永久在线 久久电影网午夜鲁丝片 我的老婆是冰山女总裁沈浪 超级女婿赵旭李晴晴全文免费阅读 28岁未成年免费完整版电影 翁与小莹最新大结局 陈说美食 恋爱的无休止境 age动漫官方网 草逼 斗罗大陆免费观看 久久免费视频 成本人动画片在线观看 都市仙尊洛尘全集目录 父爱如山动漫 噜噜射 重生之都市仙尊洛尘最新更新 朋友的尤物人妻 q友乐园网名 28岁未成年在线观看高清 昆虫记每章节内容概括 免费又色又爽又黄的视频 tube4tube8 鲤鱼乡 嘟嘟动漫网 亚洲 无码 在线 专区 35pao laoyawo xing8 另类专区av无码 温柔的谎言 电影 春梦记高清完整版 六漫画 北地胭脂 33eee avtt天堂资源网 熟女少妇人妻中文字幕 age动漫官方下载 性欧美欧洲老妇 久久不射 亚洲五月综合自拍区 新视觉影视线6080理论片 快活视频 致命的你漫画在线观看全集免费 35pao 人间情缘在线观看 我的年轻漂亮继坶 日日拍夜夜嗷嗷叫 7752 天狼影院 善良的小峓子2 肉超级多的糙汉文 黃色大片完整版免費 4hc44四虎www网址2 身为人母电影在线观看 台湾自拍偷区亚洲综合 182tv免费播放线路一线路二 japonensis日本java 护士夜夜春宵 久久水蜜桃网国产免费网 王者归来洛天 bt磁力搜索天堂 中文字幕第一页 久爱成疾在线观看在线播放 国产在线视精品在亚洲 age动漫官方下载 美国神婆星座网 亚洲中文字幕永久在线 72种性姿势真人示范 韩三千最新章节更新 sxx bt天堂在线 蝶恋花直播app最新版下载 2020抖音最火网名 保险女王 小老弟影院 伊人久久大香线蕉综合色啪 草逼 国产精品看片在线观看 日本道专区无码中文字幕 亚洲欧洲自拍图片专区 看书的网站 三级片在线观看 飞极速在线 黑白配视频在线观看 姐姐的朋友 亚洲自偷自拍另类 川娇网 男人和女人特黄的视频 另类专区av无码 2046电影未删减版在线观看 purnhurb官网是什么 新世界影院在线观看免费 s8视频 2020最新国产自产在线不卡 28岁未成年在线播放电影 榴社区 中国白胖肥熟妇bbw 最好看的2019中文字幕 玖玖热 肉超级多的糙汉文 艾草仙姑在线播放 人人天天夜夜曰曰狠狠狠 快猫记录世界纪录你 2020给个网站好人有好报 韩三千最新章节更新 japanesemature高清 国产原创剧情麻豆在线 闺蜜2韩国电影 啵乐网页 天天爱去 bt磁力猪 色土豆 久久精品国产72国产精 快穿女配被男主吃掉 国产在线精品亚洲二区 免费观看高清黄页网址大全 啵乐腐味满满 女主重生变娇媚体制最新章节 2012国语在线看免费观看 三级网 阿娇与冠希13分钟无删减视频 国语高清自产拍在线观看视频 avtt 叶凡秋沐橙小说 狼客网 都市仙尊免费阅读洛尘 治早迣简单快速的方法 佛山 秋葵app官网下载入口 污动漫 色偷偷色偷偷色偷偷在线视频 xiaosese 绝色美艳尤物胯下娇吟 污动漫 全彩口工番全漫画大全 玖玖热 316影院 欧美日韩精品一区二区在线 趣播 8个征兆说明你怀孕了 香蕉人人超人人超碰超国产 五月天婷五月天综合网 免费可以看污的完整视频网 斗罗大陆免费看 如此可爱的我们电视剧免费观看 天一影院 6080yy 久久这里只精品免费6 老子影院 年轻母亲2 小草在线观看视频播放免费 中文字幕第一页 祖女三代共侍一夫小说 国产在热线精品视频99 中国白胖肥熟妇bbw q友乐园情侣头像 2020最新国产自产在线不卡 赠我予白 新婚娇妻1一25李晶 欧式个人写真 亚洲丰满熟妇在线播放 6080yy 女神的超级赘婿赵旭全文免费阅读 q友乐园个性签名 4399看片 凌依然易谨离小说全文阅读的小说 啵乐官方网站入口链接 小草观看免费播放2019 bbox撕裂bass 啵乐漫画app官网 三级片在线 28岁未成年免费完整版电影 大伊香蕉精品视频在线 日本三级片 最新在线伦费观看中文 年轻的妻子 永恒国度 大香伊在人线免 嘟嘟动漫网 黑白配视频在线观看 一路向西在线 天狼影院手机版 朋友的尤物人妻 欲盖弄潮电影完整版在线观看 蓝色导航 北岛玲 爱琴海论坛视频播放二 年轻的小峓子4中字 顾轻舟司少帅免费阅读完整版百度小说 迅播动漫 狠狠狠的在啪线香蕉亚洲 百世汇通快递查询输入号码查询 受委屈离家出走被惩罚 附近人妇女 最好看的2018中文字幕 都是仙尊洛尘免费阅读 我和我的女儿 高清视频录播服务器器 六漫画 鲁青青 好吊妞 卡一卡二卡三免费视频 闪闪电影院 67194线路1(点击进入) 野花在线观看 八佰电影免费高清完整版在线观看 污动漫 阿娇与冠希13分钟无删减视频 夺冠在线观看免费观看完整版 征兵网 叶凡秋沐橙 口袋影院 叶君临李子染小说全文免费阅读 汤姆叔叔的小屋主要内容 皮特影院 单亲互相满足性需求 翁与小莹最新大结局 免费又色又爽又黄的视频 丰满岳乱妇 顾轻舟司少帅免费阅读完整版百度小说 青青青国产在线观看免费 六漫画 女主重生变娇媚体制 最佳情侣手机在线视频 51gan 快猫网站入口 日本高清视频在线一本视频 小小影院视频在线观看完整版 樱花动漫下载 奸魔 51gan 欧洲攻略视频免费观看 chengren 新婚娇妻宠上瘾 香蕉一本大道中文在线 另类专区av无码 超级全能学生 在线免费 啵乐官方网页 汤姆叔叔 少年阿滨第3章 一本大道香蕉中文在线视频 折腰蓬莱客肉肉 香蕉一本大道中文在线 日日拍夜夜嗷嗷叫 西西gogo高清大胆专业 亚洲 无码 在线 专区 我就是王一彤 11sasa 附近的妇女 影视大全免费观看高清版 香蕉一本大道中文在线 老鸭窝 菠萝菠萝蜜视频在线观看 ttsp 新天堂2 五月天婷五月天综合网 伊人久久大香线蕉综合色啪 佛山买房 肥肉 小说 樱花直播 可以免费观看的av毛片 给人一种阳光的头像 色五月 顾轻舟 阿娇与冠希13分钟无删减视频 拍摄指南 欧美 av亚洲 av国产 制服 佛山买房 久草原精品资源视频 春意影院免费版 粗大按摩器调教h 小蝌蚪视频 小蝌蚪视频 35pao 大团圆结局全文阅读 车祸变傻的妈妈让我爱 age动漫 作品转载 香港黄页 叶凡秋沐橙小说 汤姆高清影院 磁力天堂 尖湿锐尤早期图片 污动漫 28岁未成年免费完整版电影 国产亚洲欧美日韩一区 在线不卡日本v二区三区18 japanesefree中国寡妇 娇艳都市未删减小说 316影院 陈说美食百家号 新世界影院在线观看免费 猪猪视频 高清录播服务器 最好看的2019中文字幕 中国白胖肥熟妇bbw 至高指令未删减在线 啵乐官网入口 超级女婿赵旭李晴晴全文免费阅读 免费精品国自产网站 nana在线观看免费 手机短片 男人和女人特黄的视频 茄子视频app下载 另类专区av无码 快喵app下载官网 先锋影音亚洲中文字幕av 赠我予白 向日葵视频下载 4399电影在线观看 试看二十分钟视频视频有声 神之一手2鬼手 菠萝视频香蕉视频 s8视频 叶凡秋沐橙免费阅读 白洁被双飞 小草视频免费观看视频 17173dnf专区 sebo 顾轻舟司少帅免费阅读最新章节 天狼影院 香蕉手机网 叶凡秋沐橙小说 重生之都市仙尊洛尘最新 私人拍摄 密桃成熟时 中国雅虎 国产原创剧情麻豆在线 佛山 97gan 囗交大图片26交 丁香婷婷亚洲开心五月 nana在线观看免费 久久er热在这里只有精品66 欧美日韩国产无线码 言教授要撞坏了 鲤鱼乡 全彩口工番全漫画大全 快猫网站入口 青青青国产在线观看免费 闺蜜2在线观看完整版中字 婷婷五月天 娇艳都市未删减小说 男生喜欢的污网站免费 雍正王朝电视剧全集56 亚洲中文字幕永久在线 久久电影网午夜鲁丝片 人间情缘在线观看 菠萝视频香蕉视频 琉璃免费观看电视剧全集54 青柠网 另类专区av无码 2012中文字幕高清在线 酒色世界 佛山房价 小草免费观看在线播放 人妻日本三l级香港三级 菠萝菠萝蜜视频在线观看 大团圆结局全文阅读 sihu 小草视频免费观看视频 yy11111光电影院手机版 prohub官网入口 影视大全免费观看高清版 国产 学生 国产女合集第六部 51avi 07bbb 伊人色爱久久综合网 一路向西在线 新世界影院在线观看免费 亚洲久久综合爱久久 亚洲久久综合爱久久 汤姆高清影院 免费99精品国产自在现线 17173魔兽世界 六漫画 汤姆叔叔的小屋 十分钟在线观看视频 henhenlu yy4480 火车上爱爱好爽好刺激 又黄又湿又免费的视频 菠萝菠萝蜜视频在线观看 斗罗大陆4终极斗罗求书阁 亚洲丰满熟妇在线播放 久久不射 禁止的爱善良的小在线观看 2046电影未删减版在线观看 182tv免费播放线路一线路二 在线观看精品国产福利片 欧美videosgratis杂交 中文字幕大香视频蕉免费 毛泽东思想和中国特色社会主义理论体系概论 噜噜射 拍摄指南txt百度云全本 亚洲色tu 欧美大胆无码视频 17173dnf专区 将夜免费神马影院 淘气天尊新浪博客 新世界影院在线观看免费 都市仙尊免费阅读洛尘 avtt天堂资源网 车祸变傻的妈妈让我爱 简童沈修瑾小说免费阅读全文 国语高清自产拍在线观看视频 仙尊归来洛尘 青柠网 欧洲攻略视频免费观看 4399看片 国产欧美国产综合第一区 三级片在线观看 年轻母亲4 《禁止的爱》在线播放 千人斩官网 熟女少妇人妻中文字幕 一一影视网 酷漫屋画免费漫画平台 奇优 艾草仙姑在线播放 纯真时代 翁与小莹最新大结局 放纵的青春期全文阅读1下载 67194成l人在线观看线路 青青青国产在线观看免费 致命的你 司行霈疯狂的要顾轻舟 波多野结衣在线观看 女人本色完整版在线观看 人间情缘 都是仙尊洛尘免费阅读 国产第一页 二次元超污没有衣服无遮无挡 绝世高手陈扬最新更新章节 影视大全免费观看高清版 女朋友被窝里撒娇说要 姐姐的朋友 推荐50本熬夜看完的小说 age动漫 北岛玲 无码专区手机在线观看 大黄片 小草免费观看在线播放 henhenlu 菠萝菠萝蜜视频在线观看 日本不卡免费一区二区 28岁未成年电视免费观看 甜美的咬痕被禁的一话 一路向西在线 车祸变傻的妈妈让我爱 都市仙尊洛尘全集目录 啵乐app下载 野花在线观看 cba直播在线观看高清 任你躁在线精品免费 欧美大胆无码视频 六漫画 msn日本 香蕉一本大道中文在线 趣播 小小免费视频在线观看 欧美色视频日本片免费 非会员试看120秒体验区 graphis官网 车祸变傻的妈妈让我爱 小小免费视频在线观看 樱桃搜索 磁力天堂 偷偷藏不住.txt百度云 婚后试爱在线观看 打赌输了答应任何条件 graphis官网 唐朝tv 国产 日产 欧美最新 致命的你漫画在线观看全集免费 幸福花园 avtt 97gan aiwomen 漂亮女人在线全集免费 玉米男孩图片 最新在线伦费观看中文 秋葵app官网下载入口 闺蜜2在线观看完整版免费 歪歪漫画-动漫首页 小老弟影院 快猫下载 色土豆 染指之后 看书的网站 性欧美欧洲老妇 菠萝菠萝蜜免费视频 叶凡秋沐橙免费阅读完整版 久久er热在这里只有精品66 一本大道香蕉中文在线视频 私人拍摄 爱情鸟在线观看视频 色豆网 重生之都市仙尊洛尘最新更新 免费黄色片 顾轻舟司行霈完整版全文免费阅读 人妻无奈迎合粗大 超级全能学生 寡妇和大狼交 永久免费的网站观看 身为人母免费播放电影 言教授要撞坏了 yy11111光电影院手机版 试看二十分钟视频视频有声 meiguoshici 影视大全免费观看全集 qimi 我和小姪女小婷全文 蜜芽tv永久网站入口 182tv免费播放线路一线路二 和搜子同屋的日子2在线 汅动漫在线观看全集免费 90后宝妈雯雪百家号 免费99精品国产自在现线 陈说美食 免费黄色片 鲁青青 破膜后高清图 最后的深爱免费观看 一本到高清在线视频观看 2828 啵乐网页 胖妹做饭视频陈说美食 烈火军校免费观看完整版看全集 诸天万界推倒女主角 蓝色导航 q友乐园个性签名 6080yy anquye 山里汉宠妻无度全文免费 年轻的小婊3中文字 艳女伦交 国产亚洲欧美日韩一区 身为人母电影在线观看 小草观看免费播放2019 graphis图片 丝瓜视频污 uoco 青青河边草免费观看2019 国产原创剧情麻豆在线 高清120秒动态图试看5次 台湾自拍偷区亚洲综合 qq头像q友乐园 北地胭脂 我和黑大佬的365天高清中文翻译 jizzjizz 微拍网 q友乐园头像 都市重生修仙洛尘最新 小蝌蚪视频 麻豆传媒视频 洗衣屋 热久久 131高清图片 久草原精品资源视频 破外女出血在线视频高清在线 川娇网 熟女少妇人妻中文字幕 北地胭脂 口袋影院 父爱如山动漫 佛山买房 都市修仙洛尘最新章节 bt天堂在线 小草在线观看视频播放免费 幸福花园 龚玥菲版新梅瓶在线观看 温柔的谎言 电影 狠狠狠的在啪线香蕉亚洲 人妻日本三l级香港三级 琉璃免费观看电视剧全集54 日本一区二区 鲤鱼乡 国产精品看片在线观看 长日光阴 重生之都市修仙洛尘 第一精品福利导福航 182tv免费播放线路一线路二 夺冠在线观看免费观看完整版 恋爱的无休止境 樱桃小视频 锦衣天下电视剧西瓜免费 永久免费的网站观看 316影院 一品道门免费视频日本 高清录播服务器 宅男的天堂 将军夫人又跑了小说 我本港岛电影人 人间情缘 28岁未成年在线播放电影 给人一种阳光的头像 欧美观看免费全部完 id002 顾轻舟小说 国产精品视频每日更新 33ee 猪蜜蜜电视剧大全 2012中文字幕视频 一本到高清在线视频观看 小草在线影院观看在线播放 伊人久久大香线蕉综合色啪 斗罗大陆免费观看完整版在线观看 长日光阴 啵乐腐味满满网站 热热色
<蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <文本链> <文本链> <文本链> <文本链> <文本链> <文本链>